Item Contract # Job No. 201-109-01-1C & 2C
Contract Name: South Lakeshore Drive - Reconstruction, Hayes Avenue and Jackson Park
Location Lakeshore Drive South
Owners Name: Chicago Department of Transportation
Contract Manager (CM) Aaron Tubbs - Walsh Construction
CM Address 929 W. Adams Blvd. Chicago, IL 60607
Description of Work Executed all carpentry work, rebar installation and concrete placement to complete the drainage junction chambers for street drainage systems on Lakeshore Drive.
BCC Role: Subcontractor to Walsh Construction - 100% of work completed by BCC internal forces
Contract Amount $: $ 215,000.00
% Completed Completed
Est Completion Date Completed on April 1, 2002
BCC Project Manager Tim Jenkins 773-842-6965
Status of Contract Completed on time-on schedule