Broadway
Consolidated Company's extensive expertise in concrete work enables
them as sub-contractor to lead the way in construction of this
new south side children's hospital. From placement of concrete
walls to carpentry forming, Broadway is once again dedicated to
bringing in the job on time and within budget.
One Broadway
strongpoint is asking questions to learn about the whole job,
not just their own part. An informed partner is a greater asset
to the team effort and Broadway makes this extra step standard
practice.
|

|
| Item |
Contract
# CONCRETE |
| Contract
Name: |
University
of Chicago Comer Children's Hospital (New Construction) |
| Location |
57th
Street & Maryland Avenue, Chicago IL |
| Owners
Name: |
University
of Chicago |
| Contract
Manager (CM) |
Mortenson
/ Meyne Joint Venture - Detoy James - Project Engineer |
| CM
Address |
850
East 58th Street, Chicago IL 60637, (773)667-2975 |
| Description
of Work |
Requirements
consist of placing all concrete walls, decking, support structures
and carpentry forming, to concrete for a new construction 8 floor
building |
| BCC
Role: |
Subonctractor
to Mortenson / Meyne Joint Venture |
| Contract
Amount $: |
$
2,198,000.00 |
| %
Completed |
100% |
| Est
Completion Date |
Completed |
| BCC
Project Manager |
Margaret
Garner - (312) 491-0330 |
| Status
of Contract |
Completed |
|
|
|